From University Design and Construction Wiki
Jump to: navigation, search

Contents

Project Name

Dairy Facilities
  • This project provides for the design and construction of replacement facilities at the Dairy Cattle Center. Those facilities currently identified for replacement include a free-stall barn, a milking parlor and milk room, and a research barn.


Status

  • Notice to proceed issued on October 14, 2002. Project is complete.


Project Information

Project Title Dairy Facilities
Building Number 471 - Pump House
472 - Dry Stack Manure Barn
473 - Free Stall Barn
474 - Milking Center
Project Manager Bruce Ferguson
Planning, Design & Construction
540 231-6449
Architect/Engineer Dewberry & Davis
Marion, VA
General Contractor J. Jamerson & Sons Inc.
Appomattox, VA
Gross Square Footage 54,542 (4 Buildings)
No. of Stories (Bldg. Ht.) varies
Project Budget $5,342,860
Project Completion Spring 2004


Conceptual Drawings

  • None for projects completed before June 30, 2009.


Project Photos

Click on photo to enlarge.


Contractor Schedule


Stormwater

  • Project Completed



Project information and photos provided by Planning, Design and Construction.

Contact Patrick Donohoe for photo use permissions.

Personal tools