Project Name

Airport Parallel Taxiway
  • This project is to construct a new length of taxiway adjacent to the existing airport runway. Funding for this project is being shared by the University, the Federal Aviation Administration and the Virginia Department of Aviation.


Status

  • Substantial completion in November 1999.


Project Information

Project Title Airport Parallel Taxiway
Building Number N/A
Project Manager Robert D. Livingstone
Planning, Design & Construction
540 231-6449
Architect/Engineer URS Greiner Inc.
Richmond, VA
General Contractor Allegheny Construction Company, Inc.
Roanoke, VA
Gross Square Footage N/A
No. of Stories (Bldg. Ht.) N/A
Project Budget $3,128,500
Project Completion Oct-99


Conceptual Drawings

  • None for projects completed before June 30, 2009.


Project Photos

Click on photo to enlarge.


Contractor Schedule

Stormwater

  • Project Completed