Project Name

Boiler Pollution Controls
  • This project is to add pollution controls to the primary boiler to comply with current emission standards.


Status

  • Substantial completion issued in February, 2007.


Project Information

Project Title Boiler Pollution Controls
Building Number N/A
Project Manager J. W. Wood
Planning, Design & Construction
540 231-6449
Architect/Engineer RMF Engineering, Inc.
Baltimore, MD
General Contractor WACO (equipment)
Covington, VA
Gross Square Footage N/A
No. of Stories (Bldg. Ht.) N/A
Project Budget $5,480,770
Project Completion Feb.-2007


Conceptual Drawings

  • None for projects completed before June 30, 2009.


Project Photos

Click on photo to enlarge.


Contractor Schedule


Stormwater

  • Project Completed



Project information and photos provided by Planning, Design and Construction.

Contact Patrick Donohoe for photo use permissions.