Improve Kentland Facilities
  • THE PROJECT INCLUDES NEW CONSTRUCTION OF THREE BUILDINGS TO REPLACE SIX DETERIORATED BUILDINGS. THE THREE NEW BUILDINGS INCLUDE AN 11,000 GROSS SQUARE FOOT METABOLISM RESEARCH LABORATORY, A 7,700 GROSS SQUARE FOOT APPLIED REPRODUCTION FACILITY, AND 10,200 GROSS SQUARE FEET OF ARENA AND ANIMAL HOLDING SPACES. THE TOTAL SCOPE OF THE PROJECT IS 28,900 GROSS SQUARE FEET THAT WILL REPLACE 27,300 GROSS SQUARE FEET OF OUTDATED FACILITIES. THE SCOPE OF THE PROJECT IS BASED ON REPLACING THE SCOPE OF EXISTING FACILITIES FOR AN ESTABLISHED HERD WITH EQUAL CAPACITY NEW FACILITIES.


Status

  • Project is in design. Currently evaluating the release of an early bid package to expedite the start of construction.


Project Information

Project Title Improve Kentland Facilities
Building Number TBD
Project Manager Todd Shelton
University Design & Construction
540 231-6449
Architect/Engineer Spectrum Design, PC -
Roanoke, VA
General Contractor Name
Address
Gross Square Footage 28,900 (3 Buildings)
No. of Stories (Bldg. Ht.) Varies
Project Budget $7,600,000
LEED Certification Level N/A
Project Completion TBD


Conceptual Drawings

Click on photo to enlarge.


Project Photos

Click on photo to enlarge.


Contractor Schedule


Stormwater

  • [Future Link]



Project information and photos provided by Planning, Design and Construction.

Contact Patrick Donohoe for photo use permissions.

Personal tools