Marching Virginians Facility

From University Design and Construction Wiki
Jump to: navigation, search

Contents

Project Name

Marching Virginians Facility
  • This project includes new construction of an equipment storage building, a covered open-air practice pavilion, and a soccer-size artificial turf field. The approximately 4,300 GSF building will provide the Marching Virginians with restrooms, lockers, instrument storage space, and a drum line room for percussion instruments. The 4,000 SF pavilion will be attached to the building and will provide a protected area for the Marching Virginians to practice during inclement weather. A lighted, soccer-size artificial turf field will be shared with Recreational Sports.



Status

  • Notice to Proceed on September 30, 2014. The project is substantially complete on 6/30/15.


Project Information

Project Title Marching Virginians Facility
Building Number 0198
Project Manager David Chinn
University Design & Construction
540 231-6449
Architect/Engineer Thompson + Litton
Radford Virginia
General Contractor The Snyder Company, Inc.
Blacksburg, VA.
Gross Square Footage 4,352
No. of Stories (Bldg. Ht.) 1
Project Budget $4,750,000
LEED Certification Level N/A
Project Completion Summer 2015


Conceptual Drawings

Click on photo to enlarge.


Project Photos


Click on photo to enlarge.


Contractor Schedule


Stormwater

  • [Future Link]



Project information and photos provided by Planning, Design and Construction.

Contact Patrick Donohoe for photo use permissions.