Project Name

Worsham Field
  • This project will replace the turf on Worsham Field (Lane Stadium) during the summer of 2001.


Status

  • Project complete.


Project Information

Project Title Worsham Field
Building Number N/A
Project Manager Todd Shelton
Planning, Design & Construction
540 231-6449
Architect/Engineer Draper Aden Associates
Blacksburg, VA
General Contractor Burton F. Clark
Delhi, NY
Gross Square Footage N/A
No. of Stories (Bldg. Ht.) N/A
Project Budget $1,366,500
Project Completion Summer-01



Conceptual Drawings

  • None for projects completed before June 30, 2009.


Project Photos

Click on photo to enlarge.


Contractor Schedule


Stormwater

  • Project Completed



Project information and photos provided by Planning, Design and Construction.